1、【
单选题
】
communications is best described as:
[2.5分]
、
an exchange of information.
、
providing written or oral directions.
、
consists of senders and receivers
、
effective listening.
、
all of the above
答案:
2、【
单选题
】
the highest degrees of project risk and uncertainty are associated with the following phase of the project:
[2.5分]
、
conceptual
、
execution
、
cut-over
、
post project evaluation
、
a and d only
答案:
3、【
单选题
】
the most common types of schedules are gantt charts, milestone charts, line of balance, and:
[2.5分]
、
networks.
、
time phased events.
、
calendar integrated activities.
、
a and c only.
、
b and c only.
答案:
4、【
单选题
】
fixed price contracts place more risk on the:
[2.5分]
、
owner
、
buyer
、
seller
、
contractor
、
c or d
答案:
5、【
单选题
】
which of the following is often overlooked in achieving effective communication?
[2.5分]
、
speaking clearly
、
listening
、
interpreting
、
maintaining eye contact
、
manipulating the conversation
答案:
6、【
单选题
】
life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. life cycle costing categories include the cost
of ( ), ( ), and ( ).
[2.5分]
、
r & d, maintainability, operation and support.
、
r & d, production, operation and support.
、
acquisition, operations, maintenance.
、
production, operations, maintenance.
、
none of the above
答案:
7、【
单选题
】
which type of contract requires that the buyer keep the tightest labor/material cost control?
[2.5分]
、
cost plus incentive fee
、
cost plus percentage of costs
、
cost plus fixed fee
、
firm fixed price
、
firm fixed price plus incentive
答案:
8、【
单选题
】
management by objectives assumes that the team:
[2.5分]
、
is receptive to an unstructured environment.
、
does not require close supervision.
、
possesses a self directed philosophy
、
identifies with project objectives.
、
all of the above.
答案:
9、【
单选题
】
a task-oriented family tree of activities is a:
[2.5分]
、
detailed plan.
、
linear responsibility chart.
、
work breakdown structure.
、
cost account coding system.
、
work package description.
答案:
10、【
单选题
】
quality may be defined as:
[2.5分]
、
conformance to requirements.
、
fitness for use.
、
continuous improvement of products and services
、
appeal to the customer
、
all of the above except b
答案:
11、【
单选题
】
adding 5 people to a 4 person team increases the communication channels by a factor of:
[2.5分]
、
2 times
、
3 times
、
4 times
、
5 times
、
6 times
答案:
12、【
单选题
】
since risk is associated with most projects, the best course of action is to:
[2.5分]
、
cover all project risks by buying appropriate insurance
、
ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
、
avoid projects with clear and present risks
、
eliminate all known risks prior to the execution phase of the project
、
identify various risks and implement actions to mitigate their potential impact
答案:
13、【
单选题
】
cost management includes:
[2.5分]
、
cost estimating/forecasting.
、
cost budgeting/cost control.
、
cost applications.
、
all of the above.
、
a and b only.
答案:
14、【
单选题
】
the process of choosing/documenting the best approach to achieve the project objectives is part of:
[2.5分]
、
the scope baseline.
、
scope authorization
、
scope definition
、
scope planning.
、
all of the above.
答案:
15、【
单选题
】
time management is the allocation of time in a project's life cycle through the process of:
[2.5分]
、
planning
、
estimating.
、
scheduling.
、
controlling
、
all of the above.
答案:
16、【
单选题
】
participative management:
[2.5分]
、
involves the solicitation of information from all team members.
、
assumes that members avoid work and responsibility.
、
suggests the sharing of power and decision making.
、
employs a theory x style of leadership.
、
a and c
答案:
17、【
单选题
】
a comprehensive definition of scope management would be:
[2.5分]
、
managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
、
approval of the scope baseline.
、
approval of the detailed project charter.
、
configuration control.
、
approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
答案:
18、【
单选题
】
the auditing function that provides feedback about the quality of output is referred to as:
[2.5分]
、
quality control.
、
quality planning.
、
quality assurance.
、
quality improvement
、
all of the above.
答案:
19、【
单选题
】
the lowest dollar amount 'at stake' is associated with the following phase of the project:
[2.5分]
、
conceptual
、
execution
、
cut-over
、
post project evaluation
、
a and d only
答案:
20、【
单选题
】
cost plus percentage of cost contracts are more desirable for the:
[2.5分]
、
owner
、
buyer
、
seller
、
contractor
、
c or d
答案:
21、【
单选题
】
the major disadvantage of a bar chart is:
[2.5分]
、
lack of time-phasing.
、
cannot be related to calendar dates.
、
does not show activity interrelationships.
、
cannot be related to manpower planning.
、
cannot be related to cost estimates.
答案:
22、【
单选题
】
management styles associated with production environments, such as assembly lines commonly include:
[2.5分]
、
a directing style of leadership.
、
a lack of confidence in their workers
、
assumption that workers lack ambition and dislike responsibility
、
a theory x style of leadership
、
all of the above.
答案:
23、【
单选题
】
quality management:
[2.5分]
、
is another name for careful inspections.
、
is inversely related to productivity.
、
is primarily the responsiblity of management.
、
is primarily the responsibility of the workers.
、
is essentially a motivational technique.
答案:
24、【
单选题
】
which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
[2.5分]
、
cost plus incentive fee
、
cost plus percentage of costs
、
cost plus fixed fee
、
firm fixed price
、
firm fixed price plus incentive
答案:
25、【
单选题
】
methods and techniques used to examine cost and technical data are called feasibility studies. the economic aspects of a feasibility study
include interest rates, present worth factors, operating costs, depreciation and ( ).
[2.5分]
、
capitalization costs.
、
technical skill requirements.
、
technology forecasting.
、
strategic marketing intelligence.
、
all of the above.
答案:
26、【
单选题
】
risk management allows the project manager and the project team to:
[2.5分]
、
eliminate most risks during the planning phase of the project
、
identify project risks
、
identify impacts of various risks
、
plan suitable responses
、
b, c and d only
答案:
27、【
单选题
】
scheduling is the process by which decisions are made concerning:
[2.5分]
、
tasks to be accomplished.
、
personnel/organization that will be assigned to accomplish the task.
、
time when the tasks are to be completed.
、
all of the above.
、
a and c only.
答案:
28、【
单选题
】
standard of purchased material:
[2.5分]
、
simplifies inventory control
、
reduces the risk of obsolescence
、
reduces cost of purchasing and storage
、
all of the above.
、
a and c only.
答案:
29、【
单选题
】
the basic elements of communication include:
[2.5分]
、
listening, talking and sign language.
、
communicator, encoding, message, medium, decoding, receiver, and feedback
、
clarity of speech and good listening habits
、
reading, writing and listening
、
all of the above
答案:
30、【
单选题
】
the "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
[2.5分]
、
work packages.
、
subtasks.
、
tasks.
、
code of accounts.
、
integration points.
答案:
31、【
单选题
】
which of the following would most likely increase the accuracy of estimating the project cost?
[2.5分]
、
pricing out the work at lower levels in the work breakdown structure.
、
using historical data.
、
talking to people who have worked on similar projects.
、
all of the above.
、
a and c only.
答案:
32、【
单选题
】
the utility of network-based schedules:
[2.5分]
、
reveals interdependencies.
、
facilitates "what if" exercises.
、
highlights critical activities.
、
provides information on resource requirements, time requirements and tradeoffs.
、
all of the above.
答案:
33、【
单选题
】
the way a project manager sends and receives information depends upon:
[2.5分]
、
how others relate to the project manager
、
the project manager's level in the organizational hierarchy
、
the size and nature of the project
、
the project manager's salary and age
、
the number of projects going on at one time in the company
答案:
34、【
单选题
】
a variance envelope has been established on a project. the envelope goes from +-30% in r&d to +-5% during manufacturing. the reason for
the change in thickness of the envelope is because:
[2.5分]
、
the management reserve has been used up.
、
the accuracy of the estimates in manufacturing are worse than the estimates in r &
、
tighter controls are always needed as a project begins to wind down.
、
of the personal desires of the project sponsor.
、
of none of the above
答案:
35、【
单选题
】
cost of quality is:
[2.5分]
、
associated with non-conformance to specifications and requirements.
、
primarily caused by poor workmanship of workers who are building or manufacturing the product.
、
used to determine whether a quality management program is suitable for a given project.
、
negligible for most large projects.
、
a and b
答案:
36、【
单选题
】
uncertainty refers to a situation where:
[2.5分]
、
the outcomes are known but their probabilities are high
、
the outcomes and their probabilities are known
、
neither the outcomes nor their probabilities are known
、
states of nature can change at any time
、
probabilities of various states of nature can change at any time
答案:
37、【
单选题
】
which of the following is closet to deming's definition of quality:
[2.5分]
、
conformance to requirements.
、
fitness for use.
、
continuous improvement of products and services.
、
customer focus.
、
all of the above.
答案:
38、【
单选题
】
management plans include all of the following except:
[2.5分]
、
organization of project.
、
job descriptions.
、
policies and procedures.
、
linear responsibility charts.
、
scope baseline.
答案:
39、【
单选题
】
the japanese resource management model exhibits:
[2.5分]
、
a cooperative spirit of goal setting.
、
non-specialized career paths
、
frequent changes in team assignments
、
a theory z style of management
、
all of the above.
答案:
40、【
单选题
】
it is useful to conduct project risk assessment according to the project's
[2.5分]
、
charter
、
statement of work
、
work breakdown structure
、
network
、
budget
答案: