1、【
单选题
】
creation of project objectives:
[2.5分]
、
allows for data collection and analysis and progress reporting against which standards of performance can be measured.
、
is accomplished by selection of measurable variables against which performance can be judged.
、
is required before funding of the project by the project sponsor.
、
all of the above.
、
a and b only
答案:
2、【
单选题
】
a legally binding document offered unilaterally is a ( ) .
[2.5分]
、
purchase order
、
scope of work description
、
contract stipulation
、
level of effort proposal
、
request for proposal
答案:
3、【
单选题
】
a technical requirement has which of the following characteristics:
[2.5分]
、
easy to understand
、
a communication tool between the user and the design team
、
written in non-technical language
、
developed in cooperation with the user
、
typically describe physical dimensions and performance requirements
答案:
4、【
单选题
】
during which phase of the project life cycle is the amount at stake lowest?
[2.5分]
、
concept
、
development
、
execution
、
conclusion
、
c and d
答案:
5、【
单选题
】
if a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project
manager should assume:
[2.5分]
、
the message was understood
、
the message was not understood
、
the subordinate discarded the information
、
the information was not appropriate
、
none of the above.
答案:
6、【
单选题
】
techniques that can improve communication include:
[2.5分]
、
establishing a single, one-way communications channel
、
avoiding face-to-face communication
、
using redundancy (i.e. saying it two different ways) whenever possible
、
disregarding the sensitivity of your receiver
、
all of the above.
答案:
7、【
单选题
】
the delphi method is well-suited for:
[2.5分]
、
decision-making
、
forecasting
、
overhead rate estimating
、
all of the above
、
a and b only
答案:
8、【
单选题
】
inspection of a complex project according to specifications is accomplished by ( ).
[2.5分]
、
inspection by attributes.
、
cyclical inspection
、
quality conformance inspection
、
original inspection
、
none of the above.
答案:
9、【
单选题
】
the zero defects concept
[2.5分]
、
is a performance standard for management
、
is a motivational technique that promotes "doing it right the first time".
、
is used by management to communicate to all employees that everyone should do things right the first time.
、
a and c.
、
b and c
答案:
10、【
单选题
】
what tool have project managers come to use to identify all of the costs associated with a project.
[2.5分]
、
a bill of materials
、
a gantt chart
、
an arrow diagram network.
、
a work breakdown structure.
、
b and c only.
答案:
11、【
单选题
】
the difference between the bcws and the bcwp is referred to as the:
[2.5分]
、
schedule variance
、
cost variance.
、
estimate of completion
、
actual cost of the work performed
、
none of the above
答案:
12、【
单选题
】
"paraphrasing" is most closely associated with which part of the communication process?
[2.5分]
、
encoding
、
decoding
、
barriers
、
feedback
、
none of the above.
答案:
13、【
单选题
】
( ) is a receipt issued by a carrier for merchandise to be delivered to a party at some destination.
[2.5分]
、
proforma invoice
、
inspection certificate
、
packing list
、
bill of lading
、
none of the above.
答案:
14、【
单选题
】
a program is characterized as:
[2.5分]
、
a grouping or related tasks lasting one year or less.
、
a unique undertaking having a definite time period.
、
a grouping of similar projects having no definite end that supports the product(s) from cradle to grave.
、
a project with a cost over $1 million.
、
none of the above.
答案:
15、【
单选题
】
a gantt chart is useful in determining:
[2.5分]
、
the level of effort for a task
、
when a task starts and stops
、
how tasks are related to each other
、
who is assigned to do a task
、
all of the above.
答案:
16、【
单选题
】
a contract originated bilaterally may be developed by ( ) .
[2.5分]
、
quotation request from suppliers
、
proposal request
、
bid invitation release
、
b and c
、
all of the above.
答案:
17、【
单选题
】
in a matrix organizational form, which factor(s) make it difficult for a project manager to provide a valid input into the employee's performance
review?
[2.5分]
、
not working directly with the assigned functional employees
、
employees spend only a short amount of time assigned to the project
、
not being knowledgeable enough to evaluate employees on technical judgment
、
all of the above
、
a and b only
答案:
18、【
单选题
】
from an operating or functional perspective, there are various objectives of purchasing and materials management. which is not one of these
objectives?
[2.5分]
、
to buy competitively
、
to support company operations with an uninterrupted flow of materials and services
、
to develop reliable and effective sources of supply
、
to achieve maximum integration with the other departments of the firm
、
to attain approval from each department of every purchase
答案:
19、【
单选题
】
upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are
referred to as the:
[2.5分]
、
baseline costs
、
budgeted costs.
、
estimates upon completion costs
、
scheduled costs
、
none of the above
答案:
20、【
单选题
】
in order to achieve long-term quality improvements, management must do the following:
[2.5分]
、
motivate the employees with seminars, contests, and institute programs such as "quality improvement' day.
、
create a quality control department and give the head of the department ultimate responsibility for quality improvement.
、
implement of a formal quality control program with worker and management involvement.
、
establish financial incentive packages for worker.
、
a and d
答案:
21、【
单选题
】
which of the following is not a definition to determine a product's ability to operate as intended?
[2.5分]
、
distance
、
performance
、
function
、
condition
、
all are definitions
答案:
22、【
单选题
】
team members want to work for a project manager that can provide them with career path planning. in which organizational form is career
path planning difficult for project employees?
[2.5分]
、
matrix
、
pure project
、
project coordinator
、
project expediter
、
classical/traditional
答案:
23、【
单选题
】
the swiftest and most effective communications take place among people with
[2.5分]
、
common points of view
、
dissimilar interests
、
advanced degrees
、
the ability to reduce perception barriers
、
good encoding skills
答案:
24、【
单选题
】
a work breakdown structure is most useful for:
[2.5分]
、
identifying individual tasks for a project
、
scheduling the start of tasks
、
developing a cost estimate
、
determining potential delays
、
a and c
答案:
25、【
单选题
】
typically, during which phase in a project life cycle are most of the project expenses incurred.
[2.5分]
、
concept phase
、
development of design phase
、
execution phase.
、
termination phase.
、
none of the above
答案:
26、【
单选题
】
the primary consideration of product management is to know the ( ).
[2.5分]
、
probability of product's performance with specified parameters
、
ability the product has to perform its intended function
、
ability of a product to be produced within existing parameters
、
functionality the product will provide over its useful life
、
all of the above
答案:
27、【
单选题
】
communication always makes use of.
[2.5分]
、
symbols
、
words
、
language
、
gestures
、
all of the above.
答案:
28、【
单选题
】
fixed-price contracts place more risk on the ( ) .
[2.5分]
、
owner
、
contractor
、
seller
、
b and c
、
all of the above.
答案:
29、【
单选题
】
the reason that cost management is so difficult in project management is that:
[2.5分]
、
projects by definition and nature are non-recurring events and are therefore difficult to predict.
、
there are no tools for identifying project tasks.
、
project managers do not care about tracking costs, as only schedules are important to all project managers.
、
a and b only
、
b and c only
答案:
30、【
单选题
】
the best way to insure quality conformance is to ( ).
[2.5分]
、
distribute the responsibility to subordinates.
、
maintain total control.
、
train each worker to implement the work.
、
inspect quality into the project.
、
none of the above.
答案:
31、【
单选题
】
using visual aids during management/customer presentations will:
[2.5分]
、
hold the interest of the audience
、
strengthen the learning process by adding a visual dimension to the auditory dimension
、
stay in view longer, thus bringing back listeners who may have strayed
、
all of the above.
、
a and b only
答案:
32、【
单选题
】
the project charter is developed by:
[2.5分]
、
senior management
、
the customer
、
the project manager
、
both a and c
、
none of the above.
答案:
33、【
单选题
】
a contract is legally binding and must comprise all but one of the following:
[2.5分]
、
legal capacity
、
mutual assent
、
approved negotiations
、
consideration
、
legality
答案:
34、【
单选题
】
when a project manager is running over the budgeted costs, the project manager can typically ( ) to attempt to get the project back on
budget.
[2.5分]
、
reduce features and/or functionality
、
increase risk.
、
incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times)
、
all of the above.
、
a and b only
答案: